
CRANES (MACHINE HISTORY)
ORIGINS OF THE MODERN DAY CRANE
After a full half-century
of existence, during which it had rendered to the progress of the world
a service immeasurably greater than any dreamed of by the most
imaginative of its indomitable builders, the original Panama Railroad
was abandoned to make way for the canal in whose construction it had
been the chief instrument.
Its rails were torn up and
its roadway for the greater part of its length disappeared forever
beneath the waters of Gatun Lake. At the time of its abandonment very
little of the original road except the alignment remained. When the
American canal-builders arrived on the isthmus they found as the
transportation agency of the great task before them, a railway that in
every important respect was a quarter of a century behind the times. Its
rails were too light to sustain the weight of modern locomotives and
spoil cars, its culverts and bridges were in the same condition, and it
had only a single track. They began at once to convert it into a
double-track system, with heavy modern rails, to strengthen or rebuild
its bridges and culverts, to equip it with modern locomotives and cars,
and to supply it with an up-to-date personnel.
When
the railroad was taken over, in 1904, it had about 47 miles of a single
track and 26 miles of siding, with a rolling stock that was virtually
worthless. Five years later the total track was 160 miles: 50 miles of
main track, 35 miles of double track, all re-laid with 90 pound rails;
the equipment, thoroughly modern, comprised 150 locomotives, 1,500
freight cars, 50 passenger cars, and 4,000 spoil cars. Over the main
track there passed daily 574 trains, including 160 trains of spoil cars.
The number of passengers carried in 1910 exceeded two and a quarter
millions, the amount of commercial freight exceeded one and a quarter
million tons, and the amount of excavation spoil over its various tracks
was nearly 40,000,000 tons. It was indisputably the busiest railway,
large or small, in the world.
Fifty-two years after the
original Panama Railroad had been opened to traffic the construction of
the new one was begun. The surveys were made in 1906 and in June of the
following year work was begun.
The situation was in striking contrast with that which had confronted
the builders of the original road. Those brave pioneers had begun their
task in a pest-ridden and barren wilderness through which they must cut
their way foot by foot. They had only hand implements with which to
work, no land habitations save rude huts in swamps and jungles, no food
supply which would be considered tolerable in these times, for cold
storage was unknown, and no accurate medical knowledge with which to
counteract and overcome tropical diseases. The only road that it was
possible for them to build was along the lines of least resistance, that
is, through the river valleys, where the natural obstacles were the
least formidable. They worked waist-deep in the slimy water of swamp and
morass, piling up slowly the low embankments
upon
which to place their road-bed, and compelled to abandon all progress
from time to time because of sickness which incapacitated the entire
force. The labor which they were able to command was of the poorest and
most ignorant quality, for the curse of pestilence was upon the land and
intelligent laborers could not be induced to enter it.
A half-century later a
marvelous transformation had taken place. The isthmus had become a land
of health and plenty. The progress in mechanical invention and in the
science of engineering had improved so dramatically that such a thing as
an insurmountable natural obstacle to railway construction no longer
existed. There was an assembly on the isthmus, for the construction of the
canal, mechanical equipment which embodied all the latest and most
efficient results of scientific achievement, and which had never been
equaled in size and perfection anywhere else in the world.

There was a
work force of about forty thousand men, trained and disciplined in
construction work, well housed, well fed, and carefully safeguarded
against disease.
The railway constructors
had this equipment and this work force to draw upon as they needed, and
while the task before them was a formidable one, with such an agency at
their command it was far from being insurmountable.
What they had to do was to construct a high level railroad through what
was mainly a low level country. They needed to have the level at all points
higher than the 87 foot level of Gatun Lake. In building it they had to
cross wide and deep valleys and pierce rocky ridges.
The valleys were covered
with dense jungle growth and traversed by numerous small streams. Their
ground levels, which were from 20 to 25 feet above sea level, proved on
examination to be composed of a mass of soft clay, decomposed wood and
vegetation, from 150 to 200 feet in depth, resting upon a rock
foundation.
This
mass had near the top, a hard stratum of clay and sand from 20 to 30 feet
in thickness, but the space between this crust and the foundation was
filled with soft material.
Across these valleys (one of them
the Gatun River being about three miles in width), huge embankments were
required to
be constructed, ranging in height from 58 to 74 feet. When the weight of
these became too great for the crust to sustain, it pressed that down
upon the material beneath and forced it to the surface on either side.
This action added greatly to the amount of material in the embankments
because
the upheavals had to be counterweighted, virtually doubling the width of
the foundations. The settlement of the ground surface, varying from
25 to 60 feet, added the distance in each case to the height of the
embankment of the center or road-bed line.
Some conception of the magnitude of the task may be formed by the
statement that there were in all 167 embankments, containing a total of
16,000,000 cubic yards of material, and 164 cuts, the heaviest varying
depth from 60 to 95 feet. The three mile fill across the Gatun Valley
alone contained 5,000,000 cubic yards of material, and of the cuts one
was 95 feet deep at the
highest
point, another 84 feet, another 80 feet, and another, through solid and
very hard rock, 75 feet. It is not surprising, in view of these
formidable obstacles, that the road cost nearly $9,000,000, or about
$200,000 a mile. It had to be constructed where it was because higher
ground could only have been reached by going outside the Canal Zone and
over a much longer distance and at a larger expense.
As originally planned, the line from Gamboa to Pedro Miguel was to run
through Culebra Cut on the berm of the canal, but this route had to be
abandoned because of the slides. It became necessary to run the line
around Gold Hill through a very difficult region, for a distance of 9
1/2 miles, a change which added $1,200,000 to the cost.
The work was completed and the road was turned over formally to the
Panama Railroad Company on May 25, 1912, five years after construction
began Its length is a trifle less than that of the old line, the time of
construction was about the same, and its cost about a million dollars
greater. There all comparison ceases.
The
old line had no embankments worth mentioning, and only one cut, whose
depth was 24 feet. Such a road as the new line would have been an utter
impossibility a half-century earlier, for its difficulties would have
been insurmountable and its cost, if construction had been attempted,
would have been so tremendous as to be prohibitive.
It
is an interesting fact that the original roadway laid with ties of
native wood after being in the ground for a full half-century were in
almost perfect condition of preservation when the old line was torn up.
Many ties of similar wood have been placed on the new line, but the
greater part of its road-bed is laid with ties brought from the United
States.
During the first two years of construction the work was in charge of
Ralph Budd, chief engineer of the Panama Railroad. He resigned in
September, 1909, and was succeeded by Lieutenant Frederick Mears, USA who was in charge till the road was completed.
After World War II few
additional improvements were made to the Panama Railway, and it declined
in the late 20th century. In 1979 the US government handed over
control to the government of Panama. On the 19th June, 1998 the
government of Panama turned over control to the private Panama Canal
Railway Company ("PCRC"), with majority shares owned by the Kansas City
Southern Railroad.